Parish Hall Renovation

September 20, 2022

Renovation Progress as of 20th Sept 2022

20.9.22 contractor’s progress is at actual 30% vs scheduled 18%. Contractor is now ahead at 10% progress.
September 10, 2022

Renovation Progress as of 10th Sept 2022

10.9.22 progress contractor is 3% ahead of schedule. Scheduled as per 10.9.22 is 10%, progress on site is 13%. 1. Demolition of all existing wall to […]
September 6, 2022

Renovation Progress as of 6th Sept 2022

September 2, 2022

Constructions Loading Today

September 1, 2022

LA Signing and Handing Over of Site to the Contractor on 1st September 2022

1st September 2022 – LA Signing and Handing Over of Site to Contractor NHY Borneo Sdn Bhd